Update on the Facilities Renovations Project at the Wastewater Treatment Plant
Memorandum
On February 6, 2012, Council approved tentative award of a construction contract to Walsh Construction Company II, LLC (Walsh) in the amount of $92,929,000.00 for construction of the Facilities Renovations Project (FRP) at the City's Wastewater Treatment Plant (WWTP). The FRP consists of upgrading, rehabilitating and/or replacing the aging and deteriorating facilities at the WWTP, based on the results of extensive facilities master planning and community engagement. The action to tentatively award a construction contract was a requirement for obtaining a low interest loan from the State Revolving Fund (SRF) program administered by the Michigan Department of Environmental Quality (MDEQ) to finance construction of the FRP.
Award of the contract with Walsh was contingent upon the City making successful financial arrangements with the SRF program. This condition was satisfied through the SRF loan closing, which occurred on April 10, 2012. Notice of award was provided to Walsh on April 13, 2012, and subsequently Walsh was required to return the signed construction contract to the City along with proper insurance documents and bonds. Notice to proceed was issued to Walsh on June 8, 2012, and the preconstruction meeting was held on June 19, 2012.
Most of the required permits have been obtained as of the end of July 2012. Preliminary site activities have begun, with more extensive work coming over the next few months. WWTP staff is working closely with the consultant engineer, Malcolm Pirnie, Inc. (MPI) to assure that the project stays on schedule and the SRF loan requirements are met.
WWTP staff secured two grants for this project. The first was from the S2 Grant Program, which provides assistance to municipalities in the form of cost eligible grants for planning and design of sewage treatment works projects incurred on or after December 14, 2010. The City submit...
Click here for full text