Title
Resolution to Approve Construction Contract Change Order No. 2 with CB Asphalt Paving for Street Cut and Miscellaneous Pavement Repair - ITB No. 4624 and to Amend the FY23 Budget and Appropriate $750,000.00 from the Water Supply System Fund Balance ($1,300,00.00 increase, total contract $2,300,000.00) (8 Votes Required)
Memorandum
Attached for your approval is a resolution authorizing a construction contract change order with CB Asphalt Paving for $1,300,000.00 to perform street cut and miscellaneous pavement repair for a total contract value of $2,300,000.00. This contract is used to perform permanent asphalt repairs for utility excavations, path maintenance, parking lots, and major and local road deficiencies.
CB Asphalt Paving and True North Asphalt were the lowest qualified bidders for Street Cut and Miscellaneous Pavement Repair - ITB No. 4624. Each contractor was awarded a construction contract for $500,000.00 for a total of $1,000,000.00 to perform the work as authorized in R-20-244. True North Asphalt has not performed any pavement repairs to date and has been unresponsive. Council awarded Change Order No. 1 to increase the total contract to $1,000,000.00 on 4/5/2021, R-21-106. CB Asphalt Paving has performed quality work for three years and a change order to the construction contract is sought to increase spending authority with the sole responsive contract holder to complete necessary repairs during the final 14 months left on their contract.
Budget/Fiscal Impact: Funding for FY23 is available in the Stormwater and Sewage Disposal System Budgets and the Water Supply System unobligated fund balance. Funding for FY24 will be included in the appropriate fund budgets if so, approved by Council.
CB Asphalt Paving complies with the City's Non-Discrimination and Living Wage ordinances.
Staff
Prepared by: Paul Matthews, Public Works Assistant Manager
Reviewed by: Molly Maciejewski, Public Works Unit Manager
...
Click here for full text