Ann Arbor logo
File #: 10-0324    Version: 1 Name: 5/3/10 - 2010 Resurfacing Contract
Type: Resolution Status: Passed
File created: 5/3/2010 In control: City Council
On agenda: 5/3/2010 Final action: 5/3/2010
Enactment date: 5/3/2010 Enactment #: R-10-135
Title: Resolution to Award a Construction Contract to Barrett Paving Materials, Inc. (BID 4079, $2,574,491.50) for the 2010 Street Resurfacing Project
Attachments: 1. Resurfacing Schedule 03-31-10.pdf, 2. 2010 Resurfacing - Bid Summary .pdf, 3. 2010 Resurfacing Map.pdf, 4. Geddes Road Detour Map.pdf
Title
Resolution to Award a Construction Contract to Barrett Paving Materials, Inc. (BID 4079, $2,574,491.50) for the 2010 Street Resurfacing Project
Memorandum
Attached for your review and approval is a resolution to award a construction contract to Barrett Paving Materials, Inc. in the amount of $2,574,491.50 for the 2010 Street Resurfacing Project. This annual program is being constrained in size and scope due to the significant investment the City anticipates making to repair the Stadium Bridges over the next two year.

The 2010 Street Resurfacing Project consists of the resurfacing of approximately 5 major streets and 5 local streets located throughout the City. Attached is the street list, showing the estimated order in which the streets will be resurfaced. A list of “alternate” streets is also provided. Construction is scheduled to begin approximately May 17, 2010 and to be completed in October 2010.

The Street Resurfacing Project is created as a unit price contract with the understanding that the actual quantities used in construction will vary. Reflecting this flexibility, if any streets on the existing list are removed for any reason, such as conflicts with other projects, need for extensive utility repair, or any other unforeseen circumstances, the streets on the alternate list will be substituted in the approximate order listed. If the funds are depleted prior to the completion of all the streets listed on the attachments, the construction contract will be terminated and the balance of the streets will be deferred to a future Resurfacing Project.

Geddes Road, from Huron Parkway to Earhart Rd, which is part of this project, is a high volume road in very poor condition. The resurfacing of Geddes Road will consist of a thin mill and overlay, within the road’s existing boundaries. This is intended to improve the travelling surface and provide an additional 10 years of service life to the road at the minimal cost. No other improvements at Geddes Roa...