File #: 11-0360    Version: 1 Name: 4/19/11 - 2011 Street Resurfacing Construction Contract
Type: Resolution Status: Passed
File created: 4/19/2011 In control: City Council
On agenda: 4/19/2011 Final action: 4/19/2011
Enactment date: 4/19/2011 Enactment #: R-11-146
Title: Resolution to Award a Construction Contract to Barrett Paving Materials, Inc. (Bid No. 4139, $3,710,952.75) for the 2011 Street Resurfacing Project
Title
Resolution to Award a Construction Contract to Barrett Paving Materials, Inc. (Bid No. 4139, $3,710,952.75) for the 2011 Street Resurfacing Project
Memorandum
Attached for your review and approval is a resolution to award a construction contract to Barrett Paving Materials, Inc. in the amount of $3,710,952.75 for the 2011 Street Resurfacing Project.

The 2011 Street Resurfacing Project consists of the resurfacing of approximately 6 major streets, 6 local streets, and one intersection located throughout the City. Attached is the street list, showing the estimated order in which the streets will be resurfaced. Construction is scheduled for approximately May 2, 2011 through October 2011.

The Street Resurfacing Project is created as a unit price contract with the understanding that the actual quantities used in construction will vary. Reflecting this flexibility, if any streets on the existing list are removed for any reason, such as conflicts with other projects, need for extensive utility repair, or any other unforeseen circumstances, other streets within the city may be substituted. If the funds are depleted prior to the completion of all the streets listed on the attachments, the construction contract will be terminated and the balance of the streets will be deferred to a future Resurfacing Project.

To ensure that all funds are in place for the reconstruction of the E. Stadium Bridges and as an extra measure to properly fund all our 2011 transportation projects, we plan to execute the construction contracts for the Streets Resurfacing project soon after our determination that the TIGER II construction budget is on its way to be secured. We anticipate that time to be in the month of July 2011, with a small delay in the start of this year’s Streets Resurfacing program but with minimal impact on the project completion date.


Traffic Control During Construction
For all the streets, local access will be maintained throughout the construction. For the maj...