File #: 14-0362    Version: 1 Name: 4/7/14 - Award 2014 Resurfacing to Barrett Paving
Type: Resolution Status: Passed
File created: 3/3/2014 In control: City Council
On agenda: 4/7/2014 Final action: 4/7/2014
Enactment date: 4/7/2014 Enactment #: R-14-117
Title: Resolution to Award a Construction Contract to Barrett Paving Materials, Inc. (ITB. 4325, $3,409,000.00) for the 2014 Street Resurfacing Project
Attachments: 1. 2014 Street List.pdf, 2. 2014 Bidders List.pdf
Title
Resolution to Award a Construction Contract to Barrett Paving Materials, Inc. (ITB. 4325, $3,409,000.00) for the 2014 Street Resurfacing Project
Memorandum
Attached for your review and approval is a resolution to award a construction contract to Barrett Paving Materials, Inc. in the amount of $3,409,000.00 for the 2014 Street Resurfacing Project.  
 
This year's program consists of the resurfacing of approximately three major streets and nine local streets located throughout the City.  Attached is the expected street list. Construction is scheduled to begin approximately April 14, 2014 and to be completed in September 2014.  A tentative timeframe for construction is shown; however, the exact schedule for each street will be adjusted to best coordinate with scheduled City events (such as Art Fair, U of M home football games, and in-session school days) and other construction projects.
 
The Street Resurfacing Project is created as a unit price contract with the understanding that the actual quantities used in construction will vary.  Reflecting this flexibility, if any streets on the existing list are removed for any reason, such as conflicts with other projects, need for extensive utility repair, or any other unforeseen circumstances, other streets within the city may be substituted.  If the funds are depleted prior to the completion of all the streets listed on the attachments, the construction contract will be terminated and the balance of the streets will be deferred to a future Resurfacing Project.
 
Traffic Control During Construction
For all the streets, local access will be maintained throughout the construction.  To allow for construction on the major streets, traffic will be impacted as described below:
 
Washington (First Ave to Fourth Ave).  To minimize impacts to businesses as much as possible, much of the work will take place on a block-by block closure.  Some operations (such as paving) will require that the entire stretch be closed to traffic (detoured to adjacent blocks) while the work is taking place.  Flaggers will be utilized during the project to provide flexibility with the traffic control.  The work will be scheduled to accommodate the downtown businesses when possible.   
 
Fuller (Maiden Lane to Huron River Bridge).  Traffic will be reduced to one lane in both directions.  
 
Newport (Sunset to south of Bird Rd).  For most of the construction, traffic will be maintained around the work zones using flaggers.  During paving operations, traffic will be detoured until the asphalt has reached strength.   
 
Public Outreach
In early-March, an informational notice was mailed to all residents within the resurfacing limits of each street. The notice informed the residents of the project and provided resources to find more information (staff contacts and the web page; www.a2gov.org/RoadConstruction <http://www.a2gov.org/RoadConstruction>). For many of the roads, the notice included invitations to individual public meetings (such as St. Aubin)
 
Residents will receive another notification prior to construction and regular emails will be sent to keep people informed on the progress of the construction.  
 
Bidding
Plans and specifications were distributed electronically via BidNet and the city's Procurement webpage. Three bids were received and opened on February 28, 2014. The lowest responsible bid, in the amount of $3,409,000.00 is about 0.3% lower than the engineer's estimate of $3,418,170.  A tabulation of the bids is attached.
 
Barrett Paving Materials, Inc. received Human Rights approval.  All employees of Barrett Paving Materials, Inc., assigned to work on the project will receive compensation in accordance with the Living Wage Ordinance.
 
The project will be funded primarily from the Street Resurfacing Millage.  
Staff
Prepared by:  Nick Hutchinson, P.E., City Engineer
Reviewed by:  Craig Hupy, Public Services Area Administrator
Approved by:  Steven D. Powers, City Administrator
Body
Whereas, The City of Ann Arbor approved Street Millage Fund Capital Budget includes sufficient funds for the Annual Street Resurfacing Project;
 
Whereas, The 2014 Street Resurfacing Project includes the resurfacing and/or reconstruction of approximately 3 major streets and 9 local residential streets located throughout the City;
 
Whereas, The 2014 Street Resurfacing Project is necessary to maintain high quality streets in the City of Ann Arbor;
 
Whereas, Competitive bids were received by Procurement on February 28, 2014 and Barrett Paving Materials, Inc. was the lowest responsible bidder at $3,409,000.00;
 
Whereas, The contractual proposal sets forth the services to be performed by said company, and the payments to be made by the City therefore, all of which are agreeable to the City;
 
Whereas, It is now necessary to enter into a Contract with said company for said construction project; and
 
Whereas, Barrett Paving Materials, Inc. received Human Rights approval and its employees will receive compensation in accordance with the Living Wage Ordinance;
 
RESOLVED, That a contract in the amount of $3,409,000.00 be awarded to Barrett Paving Materials, Inc. for the construction of the 2014 Street Resurfacing Project;
 
RESOLVED, That the Mayor and City Clerk be authorized and directed to execute said contract after approval as to form by the City Attorney and approval as to substance by the City Administrator;
 
RESOLVED, That a contingency amount of $341,000.00 be established within the project budget and that the City Administrator be authorized to approve additional change orders to the construction contract with Barrett Paving Materials, Inc., not to exceed $341,000.00 in order to satisfactorily complete this project;
 
RESOLVED, That the City Administrator be authorized to take necessary administrative actions to implement this project, including issuing Traffic Control Orders for the streets included in the 2014 Street Resurfacing Project, including parking prohibition as needed in excess of 1 block and/or 90 days; and
 
RESOLVED, That the City Administrator be authorized to take the necessary administrative actions to implement this resolution.