Ann Arbor logo
File #: 09-0253    Version: 1 Name: 4/20/09 - TES Testing PSA for 2009 Major St Resurfacing
Type: Resolution Status: Passed
File created: 4/20/2009 In control: City Council
On agenda: 4/20/2009 Final action: 4/20/2009
Enactment date: 4/20/2009 Enactment #: R-09-132
Title: Resolution to Approve a Professional Services Agreement for Construction Materials Testing with TES Consultants, P.C. for the 2009 Major Street Resurfacing Project (RFP No. 721, $43,425.00)

Title

Resolution to Approve a Professional Services Agreement for Construction Materials Testing with TES Consultants, P.C. for the 2009 Major Street Resurfacing Project (RFP No. 721, $43,425.00)

Memorandum

Attached for your review and approval is a resolution to authorize a Professional Services Agreement with TES Consultants, P.C. for construction materials testing services in the amount of $43,425.00 for the 2009 Major Street Resurfacing Project. 

 

This project consists of the resurfacing of six major streets throughout the City.  The construction is scheduled for approximately April 20, 2009 through October 2009.

 

We received proposals from nine firms for the required construction materials testing services.  Project Management staff evaluated the proposals and selected TES based on the proposal, staff qualifications, past involvement with similar projects, and cost.  TES received Human Rights and Living Wage approval on March 3, 2009. 

 

Services to be performed include all the required testing for soils, aggregates, asphalt, and concrete.  Funds for the requested services are available in the project budget for the 2009 Major Street Resurfacing Project.

Staff

Prepared by:  Homayoon Pirooz, P.E., Project Management Manager

Reviewed by: Sue F. McCormick, Public Services Administrator

Approved by:  Roger W. Fraser, City Administrator

Body

Whereas, It is necessary to retain a qualified construction material testing firm to perform testing services for the 2009 Major Street Resurfacing Project;

 

Whereas, Proposals were received by Procurement and evaluated by Project Management staff on the basis of staff qualifications, past involvement with similar projects, proposed work plan, and cost;

 

Whereas, TES Consultants of Farmington Hills, Michigan has submitted to the City a proposal for the necessary services, setting forth the services to be performed by said firm and the payments to be made by the City therefore, all of which are agreeable to the City;

 

Whereas, TES Consultants received Human Rights and Living Wage approval on March 3, 2009; and

 

Whereas, The required funds for the construction materials testing services are available in the project budget for the 2009 Major Street Resurfacing Project;

 

RESOLVED, That a Professional Services Agreement with TES Consultants in the amount of $43,425.00 be approved for construction materials testing services for the 2009 Major Street Resurfacing Project;

 

RESOLVED, That the Mayor and City Clerk be authorized and directed to execute said agreement after approval as to form by the City Attorney and approval as to substance by the City Administrator;

 

RESOLVED, That City Council authorize the City Administrator to approve change orders to the agreement as needed to complete the project, in an amount not exceeding $4,300.00; and

 

RESOLVED, That the City Administrator be authorized to take the necessary administrative actions to implement this resolution.